[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255130":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1255130,839,1,"单选题","重力流排水管道铺设的顺序是（ ），排管时应将承口排向施工前进的方向。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","从上游开始顺水方向铺设",false,{"key":16,"text":17,"correct":14},"B","从上游开始逆水方向铺设",{"key":19,"text":20,"correct":14},"C","从下游开始顺水方向铺设",{"key":22,"text":23,"correct":24},"D","从下游开始逆水方向铺设",true,"重力流排水管道铺设的顺序：从下游开始逆水方向铺设",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]