[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255118":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1255118,839,1,"单选题","直埋管道接头的一级管网的现场安装的接头密封应进行（ ）的气密性检验。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20%",false,{"key":16,"text":17,"correct":14},"B","50%",{"key":19,"text":20,"correct":14},"C","80%",{"key":22,"text":23,"correct":24},"D","100%",true,"直埋管道接头的密封应符合：一级管网的现场安装的接头密封应进行100%的气密性检验。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]