[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255110":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1255110,839,1,"单选题","管棚超前支护技术施工工艺流程为（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","测放孔位→钻机就位→水平钻孔→压入钢管→移机→开挖→注浆→封口",false,{"key":16,"text":17,"correct":14},"B","钻机就位→测放孔位→水平钻孔→压入钢管→移机→开挖→注浆→封口",{"key":19,"text":20,"correct":21},"C","测放孔位→钻机就位→水平钻孔→压入钢管→移机→注浆→封口→开挖",true,{"key":23,"text":24,"correct":14},"D","钻机就位→测放孔位→水平钻孔→压入钢管→移机→注浆→封口→开挖","管棚超前支护技术施工工艺流程为：测放孔位→钻机就位→水平钻孔→压入钢管→移机→注浆（向钢管内或管周围土体）→封口→开挖。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]