[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255092":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1255092,839,1,"单选题","下列选项中不属于先张法制作预应力混凝土梁板工艺流程的是（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","调整初应力",false,{"key":16,"text":17,"correct":14},"B","张拉预应力筋",{"key":19,"text":20,"correct":21},"C","管道压浆",true,{"key":23,"text":24,"correct":14},"D","整修锚、夹具","先张法施工工艺采用先张法制作预应力混凝土构件，一般是在预制场内进行。先张法施工是在混凝土浇筑前，将预应力筋摆放于台座上，根据设计要求的控制应力对预应力筋进行张拉，并用夹具临时固定在台座上，然后浇筑混凝土，待混凝土达到一定强度后，放松预应力筋。由于预应力筋的弹性因缩，借助预应力筋与混凝土之间的粘接力，使混凝土获得预压应力",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]