[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255088":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1255088,839,1,"单选题","水下混凝土灌注施工应符合下列要求，其中说法错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","混凝土应连续灌注，中途停顿时间不宜大于30min",false,{"key":16,"text":17,"correct":18},"B","在灌注过程中，导管的埋置深度宜控制在1~3m",true,{"key":20,"text":21,"correct":14},"C","灌注混凝土时应采取防止钢筋骨架上浮的措施",{"key":23,"text":24,"correct":14},"D","灌注的桩顶标高应比设计高出0.5~1m","在灌注过程中，导管的埋置深度宜控制在2~6m",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]