[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255042":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1255042,839,1,"单选题","水泥粉煤灰碎石桩的施工工艺流程为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","桩位测量→桩机就位→钻进成孔→混凝土浇筑→移机→检测→褥垫层施工",true,{"key":16,"text":17,"correct":18},"B","桩机就位→桩位测量→钻进成孔→混凝土浇筑→移机→检测→褥垫层施工",false,{"key":20,"text":21,"correct":18},"C","桩位测量→桩机就位→钻进成孔→移机→混凝土浇筑→检测→褥垫层施工",{"key":23,"text":24,"correct":18},"D","桩机就位→桩位测量→钻进成孔→移机→混凝土浇筑→检测→褥垫层施工","水泥粉煤灰碎石桩的一般施工工艺流程为：桩位测量→桩机就位→钻进成孔→混凝土浇筑→移机→检测→褥垫层施工。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]