[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1255020":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1255020,839,1,"单选题","路基填土压实，应严格控制土壤的压实含水量在最佳含水量的±（ ）％以内。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","1",false,{"key":16,"text":17,"correct":18},"B","2",true,{"key":20,"text":21,"correct":14},"C","3",{"key":23,"text":24,"correct":14},"D","4","路基填土压实，应严格控制土壤的压实含水量在最佳含水量的±2％以内。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]