[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254885":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1254885,839,1,"单选题","施工测量的精度应根据（ ）进行施工测量。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工程设计和施工的精度要求",true,{"key":16,"text":17,"correct":18},"B","控制点的精度",false,{"key":20,"text":21,"correct":18},"C","地形",{"key":23,"text":24,"correct":18},"D","环境","施工测量的精度应根据工程设计和施工的精度要求进行施工测量。",{"id":6,"name":27,"category":28,"favorite":29},"(市政施工)基础知识","建筑工程",0]