[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254719":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254719,838,3,"判断题","单位工程有分包单位施工时，分包单位对所承包的施工项目按标准规定的程序进行检查评定，总包单位可以不参加检查评定。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"单位工程有分包单位施工时，分包单位对所承包的施工项目按标准规定的程序进行检查评定，总包单位要参加检查评定。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]