[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254696":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254696,838,3,"判断题","采用工程量清单方式招标时，工程量清单不一定要作为招标文件的组成部分，招标人应将工程量清单连同招标文件的其他内容一并发给投标人，并对其编制的工程量清单的准确性和完整性负责。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"采用工程量清单方式招标时，工程量清单作为招标文件的组成部分，招标人应将工程量清单连同招标文件的其他内容一并发给投标人，并对其编制的工程量清单的准确性和完整性负责。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]