[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254657":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254657,838,3,"判断题","第企业的成本管理责任体系包括两个方面：一是企业管理层；二是施工管理层.",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"企业的成本管理责任体系包括两个方面：一是企业管理层，其管理从投标开始止于结算的全过程，着眼于体现效益中心的管理职能；二是项目管理层，其管理以企业确定的施工成本为目标，体现现场生产成本控制中心的管理职能。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]