[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254656":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1254656,838,3,"判断题","施工阶段是项目成本发生的主要阶段，也是成本控制的重点阶段。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"成本的控制活动方法：施工阶段是项目成本发生的主要阶段，也是成本控制的重点阶段，控制的对象包括：通过劳务合同进行人工费的控制；通过定额管理和计量管理进行材料用量的控制；通过掌握市场信息，采用招标、询价等方式控制材料、设备的采购价格等。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]