[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254611":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254611,838,3,"判断题","分项工程交底包括分部工程（或重要部位、关键工艺、特殊过程）的范围、施工条件、施工组织、计划安排、特殊技术要求、技术措施、资源投人、质量及安全要求等。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"项目各现场管理的工程师负责向分包单位的施工人员进行分项工程施工技术交底，交底内容包括具体工作内容、操作方法、施工工艺、质量标准、安全注意事项。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]