[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254595":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":19},1254595,838,3,"判断题","事前对影响施工项目质量的要素严加控制，是保证施工项目质量的关键。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,"影响施工项目质量的要素有五大方面，即4M1E，指人、材料、机械、方法和环境，事前对这五方面的因素严加控制，是保证施工项目质量的关键。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]