[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254582":3},{"question":4,"library":19},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":13,"analysis":9},1254582,838,3,"判断题","编制好的施工进度计划是编制同期的各种生产资源需要量计划的重要依据，包括人力资源、材料和工程设备、施工机械、施工技术和施工需用资金等各种需要量计划。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",true,{"key":16,"text":17,"correct":18},"B","错误",false,{"id":6,"name":20,"category":21,"favorite":22},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]