[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254581":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254581,838,3,"判断题","若进度偏差大于总时差，说明此偏差对总工期无影响，但它对后续工作的影响程度，需要根据此偏差与自由时差的比较情况来确定。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"分析进度偏差是否大于总时差若进度偏差大于总时差，说明此偏差必将影响后续工作和总工期，必须采取相应的调整措施。若进度偏差小于或等于总时差，说明此偏差对总工期无影响，但它对后续工作的影响程度，需要根据此偏差与自由时差的比较情况来确定。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]