[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254577":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254577,838,3,"判断题","大多数单位工程施工进度计划是与作业计划一样均为控制性计划。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"除对跨多年度的工程因其规模庞大具有控制性作用外，大多数单位工程施工进度计划是与作业计划一样均为实施性计划。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]