[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254572":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254572,838,3,"判断题","若工程规模较大、工艺关系复杂时、制约因素较多，施工设计图纸、工程设备、特殊材料和大宗材料采购供应尚未全部清晰，为便于调整计划用横道图计划表示为妥。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"若工程规模较大、制约因素较多，施工设计图纸供给情况，工程设备、特殊材料和大宗材料采购供应情况尚未全部清晰，为便于调整计划则用网络计划图表示为妥。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]