[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254569":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254569,838,3,"判断题","若进度偏差小于或等于自由时差，说明此偏差对后续工作产生影响，应根据后续工作允许的影响程度来确定如何调整。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"若进度偏差大于自由时差，说明此偏差对后续工作产生影响，应根据后续工作允许的影响程度来确定如何调整。若进度偏差小于或等于自由时差，则说明此偏差对后续工作无影响。因此，原进度计划可以不做调整。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]