[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254560":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254560,838,3,"判断题","室外给水管道工程施工顺序：施工准备→放线挖土→沟槽预制→布管、下管→管道对口、调直稳固→管道连接→试压、冲洗、消毒→土方回填、砌阀门井。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"室外给水管道工程施工顺序：施工准备→放线挖土→沟槽验收→管道预制→布管、下管→管道对口、调直稳固→管道连接→试压、冲洗、消毒→土方回填、砌阀门井。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]