[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254547":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254547,838,3,"判断题","施工顺序反映施工活动中的工序衔接关系，应符合工艺技术规律，在一定生产力水平下是可以违反的。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"施工顺序反映施工活动中的工序衔接关系，应符合工艺技术规律，在一定生产力水平下是不能违反的。比如给水排水工程中要支架安装安排在先，管道敷设安排在后，反过来的安排是不可能也行不通的。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]