[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254525":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254525,838,3,"判断题","盘柜施工顺序：施工准备→盘柜搬运→基础型钢制作安装→盘柜就位→硬母线安装→试验整定→一、二次线连接→送电运行验收。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"盘柜施工顺序：施工准备→盘柜搬运→基础型钢制作安装→盘柜就位→硬母线安装→一、二次线连接→试验整定→送电运行验收。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]