[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254524":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254524,838,3,"判断题","阶段性施工进度计划要依施工总进度计划的控制节点为准，一般可自行调整。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"阶段性施工进度计划要依施工总进度计划的控制节点为准，一般不可自行调整。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]