[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254460":3},{"question":4,"library":20},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":17,"analysis":19},1254460,838,3,"判断题","雨水管道灌水试验的灌水高度必须到每根立管上部的雨水斗，试验持续时间1.5h，不渗不漏为合格。",[11,15],{"key":12,"text":13,"correct":14},"A","正确",false,{"key":16,"text":17,"correct":18},"B","错误",true,"雨水管道灌水试验的灌水高度必须到每根立管上部的雨水斗，试验持续时间1h，不渗不漏为合格。",{"id":6,"name":21,"category":22,"favorite":23},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]