[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254417":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254417,838,2,"多选题","建筑电气工程施工质量验收要求，参与单位工程验收时应提供的资料有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建筑电气工程的工程质量控制资料",true,{"key":16,"text":17,"correct":18},"B","建筑电气工程的工程方案实施过程",false,{"key":20,"text":21,"correct":14},"C","建筑电气工程的工程安全和功能检验及主要功能抽查记录",{"key":23,"text":24,"correct":14},"D","建筑电气工程的工程观感质量检查记录",{"key":26,"text":27,"correct":18},"E","建筑电气工程的工程的工程技术检测","ACD","建筑电气工程施工质量验收要求，参与单位工程验收时应提供的资料：建筑电气工程的工程质量控制资料；建筑电气工程的工程安全和功能检验及主要功能抽查记录；建筑电气工程的工程观感质量检查记录。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]