[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254398":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254398,838,2,"多选题","工程中涉及（ ）的专项施工方案，施工单位还应当组织专家进行论证和审查。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","深坑工程",true,{"key":16,"text":17,"correct":14},"B","地下暗挖工程",{"key":19,"text":20,"correct":21},"C","土方开挖工程",false,{"key":23,"text":24,"correct":14},"D","高大模板工程",{"key":26,"text":27,"correct":21},"E","技术难度的工程","ABD","工程中涉及深坑工程、底下暗挖工程、高大模板工程的专项施工方案，施工单位还应当组织专家进行论证和审查。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]