[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254381":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254381,838,2,"多选题","临时用电施工组织设计必须由（ ）批准后实施，实施或使用中有变更，需经重新设计和办理审批手续，并补充图纸后方可实施。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","电气专业技术人员编制",true,{"key":16,"text":17,"correct":14},"B","技术负责人审核",{"key":19,"text":20,"correct":14},"C","企业主管安全部门",{"key":22,"text":23,"correct":24},"D","技术管理人员操作",false,{"key":26,"text":27,"correct":24},"E","项目部经理","ABC","临时用电施工组织设计必须由电气专业技术人员编制、技术负责人审核、企业主管安全部门批准后实施，实施或使用中有变更，需经重新设计和办理审批手续，并补充图纸后方可实施。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]