[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254372":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254372,838,2,"多选题","工程项目施工前，施工单位项目经理部应建立质量责任制度、现场管理制度及检验制度，健全质量管理体系，配备施工技术标准，审查（ ）等资料，填写“施工现场质量管理检查记录”。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","资质证书",true,{"key":16,"text":17,"correct":14},"B","施工图",{"key":19,"text":20,"correct":14},"C","地质勘察资料",{"key":22,"text":23,"correct":14},"D","施工技术文件",{"key":25,"text":26,"correct":27},"E","施工合同文件",false,"ABCD","工程项目施工前，施工单位项目经理部应建立质量责任制度、现场管理制度及检验制度，健全质量管理体系，配备施工技术标准，审查资质证书、施工图、地质勘察资料、施工技术文件等资料，填写“施工现场质量管理检查记录”。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]