[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254334":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254334,838,2,"多选题","招标文件会对工程量提出的解释有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","不论何种情况提供的工程量清单均不作调整",true,{"key":16,"text":17,"correct":14},"B","在招标答疑会上允许提出疑问",{"key":19,"text":20,"correct":21},"C","解释招标工程",false,{"key":23,"text":24,"correct":21},"D","招标工程方案",{"key":26,"text":27,"correct":21},"E","在施工前做好技术交底工作","AB","招标文件会对工程量提出两种不同的解释，一种是不论何种情况提供的工程量清单均不作调整，另一种是在招标答疑会上允许提出疑问，后一种情况说明工程量复核的必要性。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]