[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254296":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254296,838,2,"多选题","成本的控制的对象包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","通过劳务合同进行人工费的控制",true,{"key":16,"text":17,"correct":18},"B","通过施工管理进行材料用量的控制",false,{"key":20,"text":21,"correct":14},"C","通过掌握市场信息，采用招标、询价等方式控制材料、设备的采购价格",{"key":23,"text":24,"correct":18},"D","注意工程变更等的动态因素影响",{"key":26,"text":27,"correct":14},"E","通过定额管理和计量管理进行材料用量的控制","ACE","成本的控制活动方法：施工阶段是项目成本发生的主要阶段，也是成本控制的重点阶段，控制的对象包括：通过劳务合同进行人工费的控制；通过定额管理和计量管理进行材料用量的控制；通过掌握市场信息，采用招标、询价等方式控制材料、设备的采购价格等。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]