[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254287":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254287,838,2,"多选题","施工成本是指在建设工程项目的施工过程中所发生的全部生产费用的总和，包括消耗的各种（ ）等费用，支付给生产工人的工资、奖金、工资性津贴等费用，以及进行施工组织和管理所发生的全部费用支出。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","原材料",true,{"key":16,"text":17,"correct":14},"B","辅助材料",{"key":19,"text":20,"correct":14},"C","构配件",{"key":22,"text":23,"correct":14},"D","周转材料的摊销费用或租赁费用",{"key":25,"text":26,"correct":27},"E","利润",false,"ABCD","施工成本是指在建设工程项目的施工过程中所发生的全部生产费用的总和，包括消耗的各种原材料、辅助材料、构配件、周转材料的摊销费用或租赁费用等费用，支付给生产工人的工资、奖金、工资性津贴等费用，以及进行施工组织和管理所发生的全部费用支出。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]