[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254286":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254286,838,2,"多选题","成本的控制活动要求（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","要按照计划成本目标值来控制物资采购价格，并做好物资进场验收工作，确保质量",true,{"key":16,"text":17,"correct":14},"B","注意工程变更等的动态因素影响",{"key":19,"text":20,"correct":14},"C","增强项目管理人员和全体员工的成本意识和控制能力",{"key":22,"text":23,"correct":24},"D","通过劳务合同进行人工费的控制",false,{"key":26,"text":27,"correct":24},"E","加强施工管理","ABC","成本的控制活动要求：要按照计划成本目标值来控制物资采购价格，并做好物资进场验收工作，确保质量；注意工程变更等的动态因素影响；增强项目管理人员和全体员工的成本意识和控制能力等。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]