[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254264":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254264,838,2,"多选题","整个系统联合调试和试运行试验包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","空载试运行",true,{"key":16,"text":17,"correct":14},"B","有载试运行",{"key":19,"text":20,"correct":14},"C","满负荷试运行",{"key":22,"text":23,"correct":24},"D","变负荷试运行",false,{"key":26,"text":27,"correct":24},"E","90%负荷试运行","ABC","通风与空调工程施工试验类记录有两大类。一类是单体单机的措施试验，如风管的密闭性试验、风机的单机试运行、电动或气动调节阀的单校、冷却水的水泵试运转试验等。二类是整个系统联合调试和试运行试验，包括空载试运行和有负荷试运行或满负荷试运行，这类试验结果形成的记录统称为系统调试试运行记录。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]