[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254261":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254261,838,2,"多选题","现场质量检查的内容（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","工序交接检查",true,{"key":16,"text":17,"correct":14},"B","开工前检查",{"key":19,"text":20,"correct":14},"C","隐蔽工程检查",{"key":22,"text":23,"correct":14},"D","停工后复工前的检查",{"key":25,"text":26,"correct":27},"E","图纸会审有记录",false,"ABCD","现场质量检查的内容：开工前检查；工序交接检查；隐蔽工程检查；停工后复工前的检查；分项、分布工程完工后，应经检查认可，签署验收记录；产品保护检查。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]