[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254260":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254260,838,2,"多选题","技术交底的实施包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","技术交底的准备",true,{"key":16,"text":17,"correct":14},"B","技术交底文件归档",{"key":19,"text":20,"correct":14},"C","技术交底记录",{"key":22,"text":23,"correct":24},"D","技术交底计划",false,{"key":26,"text":27,"correct":24},"E","技术交底的规划管理","ABC","技术交底的实施：明确技术交底的责任；技术交底的准备；技术交底记录；技术交底文件归档；作业中发生外部指令引起的变更与预期有较大变化者要及时向作业人员交底。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]