[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254246":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254246,838,2,"多选题","与建筑电气工程施工有关的试验记录包括（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","绝缘电阻测试记录",true,{"key":16,"text":17,"correct":14},"B","接地电阻测试记录",{"key":19,"text":20,"correct":14},"C","变配电设备检查通电满负荷测试记录",{"key":22,"text":23,"correct":14},"D","电气照明动力系统调试试运行记录",{"key":25,"text":26,"correct":27},"E","空调动力系统调试试运行记录",false,"ABCD","与建筑电气工程施工有关的试验记录包括：绝缘电阻测试记录、接地电阻测试记录、变配电设备检查通电满负荷测试记录、电气照明动力系统调试试运行记录等。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]