[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254221":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254221,838,2,"多选题","安装工程成品保护的措施包括（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","包裹",true,{"key":16,"text":17,"correct":14},"B","覆盖",{"key":19,"text":20,"correct":14},"C","封闭",{"key":22,"text":23,"correct":24},"D","罚款",false,{"key":26,"text":27,"correct":24},"E","专人负责","ABC","安装工程成品保护的措施包括：包裹、覆盖、封闭。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]