[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254216":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254216,838,2,"多选题","进度计划的调整方法主要有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","改变某些工作的逻辑关系",true,{"key":16,"text":17,"correct":14},"B","改变某些工作的持续时间",{"key":19,"text":20,"correct":21},"C","增加施工技术人员",false,{"key":23,"text":24,"correct":21},"D","增加材料设备",{"key":26,"text":27,"correct":21},"E","增加施工机械、机具","AB","进度计划的调整方法主要有：改变某些工作的逻辑关系；改变某些工作的持续时间。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]