[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254214":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254214,838,2,"多选题","影响安装工程进度的因素，建设项目外部包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设备、材料供应商违约不能如期供货",true,{"key":16,"text":17,"correct":14},"B","水、电、气等能源供给单位不能如期接通供应",{"key":19,"text":20,"correct":21},"C","施工组织管理不力",false,{"key":23,"text":24,"correct":21},"D","各专业分包单位不能如期履行分包合同",{"key":26,"text":27,"correct":14},"E","施工设计图纸不能按计划或施工设计作出重大修改","ABE","影响安装工程进度的因素，建设项目外部包括政府对建设的宏观调控；设备、材料供应商违约不能如期供货；水、电、气等能源供给单位不能如期接通供应；施工设计图纸不能按计划或施工设计作出重大修改；意外事件的出现。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]