[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254208":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254208,838,2,"多选题","工程实体的形成应是（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","符合施工顺序",true,{"key":16,"text":17,"correct":14},"B","符合工艺规律",{"key":19,"text":20,"correct":21},"C","符合施工要求",false,{"key":23,"text":24,"correct":21},"D","符合施工进度",{"key":26,"text":27,"correct":14},"E","符合当前的科学技术水平","ABE","施工活动的结果是形成工程实体，工程实体的形成是符合施工顺序、符合工艺规律、符合当前的科学技术水平，而这三个符合体现在施工进度计划编制过程中。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]