[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254207":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254207,838,2,"多选题","网络图中，对比分析实际进度与计划进度的方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","横道图比较法",false,{"key":16,"text":17,"correct":18},"B","前锋线比较法",true,{"key":20,"text":21,"correct":18},"C","S形曲线比较法",{"key":23,"text":24,"correct":18},"D","“香蕉”形曲线比较法",{"key":26,"text":27,"correct":18},"E","列表比较法","BCDE","网络图中，对比分析实际进度与计划进度的方法有：前锋线比较法、S形曲线比较法、“香蕉”形曲线比较法、列表比较法。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]