[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254205":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254205,838,2,"多选题","甲公司中标一高级写字楼机电工程，内容含给水排水工程、通风与空调工程、电气工程等多个专业分部工程，由于工程量大、工期紧，需要编制施工进度网络计划，充分利用公司资源，进行严密组织施工，才能满足工期需要。根据背景资料，回答下列问题。 本工程工期紧，如何组织施工显得尤为重要，常用施工组织方式为（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","依次施工",true,{"key":16,"text":17,"correct":14},"B","流水施工",{"key":19,"text":20,"correct":21},"C","垂直施",false,{"key":23,"text":24,"correct":21},"D","混合施工",{"key":26,"text":27,"correct":14},"E","平行施工","ABE","本工程工期紧，如何组织施工显得尤为重要，常用施工组织方式为依次施工、流水施工、平行施工。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]