[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254204":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254204,838,2,"多选题","进度计划调整的方法有（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","压缩或延长工作持续时间",true,{"key":16,"text":17,"correct":14},"B","增强或减弱资源供应强度",{"key":19,"text":20,"correct":21},"C","施工组织管理不力",false,{"key":23,"text":24,"correct":21},"D","各专业分包单位不能如期履行分包合同",{"key":26,"text":27,"correct":14},"E","在不违反工艺规律的情况下改变专业或工序衔接关系","ABE","进度计划调整的方法有：压缩或延长工作持续时间；增强或减弱资源供应强度；改变作业组织形式；在不违反工艺规律的情况下改变专业或工序衔接关系；修正施工方案。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]