[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254203":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254203,838,2,"多选题","进度控制受以下原理影响（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","循环原理",true,{"key":16,"text":17,"correct":14},"B","系统原理",{"key":19,"text":20,"correct":21},"C","静态控制原理",false,{"key":23,"text":24,"correct":14},"D","信息反馈原理",{"key":26,"text":27,"correct":14},"E","动态控制原理","ABDE","（1）施工进度计划编制中应用的循环原理、系统原理、动态控制原理和信息反馈原理等方法或原则，同样适用于资源供给计划的编制，仅是侧重点各有不同。否则两种计划的编制和执行就做不到同步协调、总体平衡。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]