[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254201":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254201,838,2,"多选题","施工项目进度控制的主要方法有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","行政方法",true,{"key":16,"text":17,"correct":14},"B","经济方法",{"key":19,"text":20,"correct":14},"C","管理技术方法",{"key":22,"text":23,"correct":24},"D","夜间加班法",false,{"key":26,"text":27,"correct":24},"E","增加人员法","ABC","施工项目进度控制的主要方法有：行政方法、经济方法、管理技术方法。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]