[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254200":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254200,838,2,"多选题","根据工程规模来分，工程项目的进度计划可以分为（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","施工总进度计划",true,{"key":16,"text":17,"correct":14},"B","单位工程施工进度计划",{"key":19,"text":20,"correct":14},"C","分部分项工程施工进度计划",{"key":22,"text":23,"correct":24},"D","控制性进度计划",false,{"key":26,"text":27,"correct":24},"E","实施性作业计划","ABC","根据工程规模来分，工程项目的进度计划可以分为：施工总进度计划、单位工程施工进度计划、分部分项工程施工进度计划。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]