[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254199":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1254199,838,2,"多选题","作业计划编制前要对（ ）等做充分的了解，并对执行中可能遇到的问题及其解决的途径提出对策，因而作业计划具有更强的可操作性。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","施工现场条件",true,{"key":16,"text":17,"correct":14},"B","人力资源配备和物资供应状况",{"key":19,"text":20,"correct":14},"C","作业面现状",{"key":22,"text":23,"correct":14},"D","技术能力情况",{"key":25,"text":26,"correct":14},"E","资金供给的可能性","ABCDE","作业计划编制前要对施工现场条件、作业面现状、人力资源配备、物资供应状况、技术能力情况和资金供给的可能性等做充分的了解，并对执行中可能遇到的问题及其解决的途径提出对策，因而作业计划具有更强的可操作性。",{"id":6,"name":30,"category":31,"favorite":32},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]