[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254197":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1254197,838,2,"多选题","施工进度计划的分类，按指导施工时间长短分类（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","年度计划",true,{"key":16,"text":17,"correct":14},"B","季度计划",{"key":19,"text":20,"correct":14},"C","月度计划",{"key":22,"text":23,"correct":14},"D","旬或周计划",{"key":25,"text":26,"correct":27},"E","总计划",false,"ABCD","施工进度计划的分类，按指导施工时间长短分类：有年度计划、季度计划、月度计划、旬或周计划等。",{"id":6,"name":31,"category":32,"favorite":33},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]