[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254189":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1254189,838,2,"多选题","施工的流向是由（ ）三个方面的要求决定的。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","保证施工进度",false,{"key":16,"text":17,"correct":18},"B","施工组织",true,{"key":20,"text":21,"correct":18},"C","缩短工期",{"key":23,"text":24,"correct":18},"D","保证施工质量",{"key":26,"text":13,"correct":14},"E","BCD","空间顺序的目的是解决施工的流向，施工的流向是由施工组织、缩短工期和保证施工质量三个方面的要求决定的。",{"id":6,"name":30,"category":31,"favorite":32},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]