[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1254181":3},{"question":4,"library":29},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":27,"analysis":28},1254181,838,2,"多选题","施工组织设计的编制的流程（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","组织编制组，明确负责人",true,{"key":16,"text":17,"correct":14},"B","收集整理编制依据，并鉴别其完整性和真实性",{"key":19,"text":20,"correct":14},"C","编制组分工，并明确初稿完成时间",{"key":22,"text":23,"correct":24},"D","工程施工合同、招标投标文件或相关协议",false,{"key":26,"text":23,"correct":24},"E","ABC","施工组织设计的编制的流程：组织编制组，明确负责人；收集整理编制依据，并鉴别其完整性和真实性；编制组分工，并明确初稿完成时间等。",{"id":6,"name":30,"category":31,"favorite":32},"(设备安装施工)专业管理实务 岗位知识","建筑工程",0]